# Cabinet clears ₹1.86 lakh crore Green Energy Corridor Phase-III with 50 GWh of batteries

URL: https://upsc.help/current-affairs/2026-10-01/green-energy-corridor-phase-three/
Date: 1 October 2026 (2026-10-01)
Source: The Hindu, Business
UPSC papers: GS3
Publisher: upsc.help (Pratidin), free and open-source UPSC Civil Services current affairs. Not affiliated with UPSC. Every fact was checked against the source reports by a separate review before publishing.

**In one line:** The Cabinet has approved a ₹1,86,405 crore scheme to strengthen State grids and add 50 GWh of batteries, so that up to 135 GW of renewable power can reach consumers by 2032-33.

The Union Cabinet chaired by Prime Minister Narendra Modi approved the Green Energy Corridor Phase-III (GEC-III) scheme on 30 September 2026. It will strengthen the Intra-State Transmission System (InSTS), the lines and substations inside each State, so that up to 135 gigawatts (GW) of renewable energy can be evacuated across States and Union Territories. The total outlay is ₹1,86,405 crore: ₹1,36,378 crore for intra-State transmission and ₹50,000 crore for 50 gigawatt-hours (GWh) of Battery Energy Storage Systems (BESS). The Centre will give ₹54,082 crore as central financial support, about 29% of the outlay. The work is to be completed by 2032-33.

Batteries can be placed at the renewable developer's end or at any other location of importance on the grid. They are meant to tackle the intermittency of solar and wind, transmission congestion, curtailment (when generators are told to cut output because the grid cannot take it) and demand in non-solar hours. Greenfield projects will be awarded through Tariff Based Competitive Bidding (TBCB) and brownfield work on a cost-plus basis. State Transmission Utilities will be the implementing agencies, and Transmission Service Providers will build, own, operate and maintain the assets. The government says the scheme will help reach 900 GW of installed non-fossil capacity by 2035.

GEC-III is far larger than the earlier phases. Phase-I covered eight renewable-rich States for about 24 GW at a cost of ₹10,141.68 crore. Phase-II, approved in January 2022, covered seven States for about 20 GW, with ₹12,031.33 crore of outlay, 33% central assistance, about 10,750 circuit km of lines and 27,500 MVA of substations, over 2021-22 to 2025-26. Briefing the media, Union Minister Ashwini Vaishnaw said transmission has to be in place before renewable capacity is added.

## Prelims facts

- GEC-III, approved on 30 September 2026, has an outlay of ₹1,86,405 crore and central financial support of ₹54,082 crore.
- It strengthens intra-State transmission to evacuate up to 135 GW of renewable energy and adds 50 GWh of battery storage by 2032-33.
- Greenfield projects go through Tariff Based Competitive Bidding; brownfield work is on a cost-plus basis; State Transmission Utilities implement.
- GEC-II (approved January 2022) was ₹12,031.33 crore for about 20 GW in seven States, with 33% central assistance.
- The scheme is linked to the target of 900 GW of installed non-fossil capacity by 2035.

## Quick recall

- **GEC-III total outlay** ₹1,86,405 crore (₹1,36,378 crore transmission plus ₹50,000 crore battery storage).
- **GEC-III central financial support** ₹54,082 crore.
- **Renewable capacity GEC-III aims to evacuate** Up to 135 GW.
- **Battery storage under GEC-III** 50 GWh of Battery Energy Storage Systems.
- **GEC-III completion target** 2032-33.
- **Implementing agencies for GEC-III** State Transmission Utilities.
- **GEC-II at a glance** Approved January 2022: ₹12,031.33 crore, about 20 GW, seven States, 33% central assistance, 2021-22 to 2025-26.
- **Non-fossil capacity target the scheme supports** 900 GW of installed non-fossil capacity by 2035.

## Prelims practice question

With reference to the Green Energy Corridor Phase-III scheme approved in September 2026, which one of the following statements is correct?

(a) It funds only inter-State transmission lines built by central agencies
(b) It combines intra-State transmission with battery energy storage systems
(c) It is financed entirely by the Union Government
(d) It applies only to the eight States covered in Phase-I

Answer: (b) It combines intra-State transmission with battery energy storage systems. GEC-III funds Intra-State Transmission Systems (₹1,36,378 crore) and 50 GWh of battery storage (₹50,000 crore). Central support is ₹54,082 crore, about 29% of the outlay, not the whole. It covers States and Union Territories generally, not only Phase-I States.

## UPSC previous-year questions this connects to

- UPSC Mains 2022, GS3: Do you think India will meet 50 percent of its energy needs from renewable energy by 2030? Justify your answer. How will the shift of subsidies from fossil fuels to renewables help achieve the above objective? Explain. (https://upsc.help/pyq/q181-do-you-think-india-will-meet-50/)
  How to use this story in the answer: Use it to argue that India's renewable goals hinge on transmission and storage, and to show public money now flowing into grid integration of renewables.
- UPSC Mains 2021, GS3: Explain the purpose of the Green Grid Initiative launched at World Leaders Summit of the COP26 UN Climate Change Conference in Glasgow in November, 2021. When was this idea first floated in the International Solar Alliance (ISA)? (https://upsc.help/pyq/q254-purpose-green-grid-initiative-launched-world-leaders/)
- UPSC Mains 2018, GS3: "Access to affordable, reliable, sustainable and modern energy is the sine qua non to achieve Sustainable Development Goals (SDGs)". Comment on the progress made in India in this regard. (https://upsc.help/pyq/q180-access-affordable-reliable-sustainable-modern-energy-sine/)
  How to use this story in the answer: Use the Green Energy Corridor phases as evidence of India's progress in building the grid needed for reliable, sustainable energy, and of the scale still required.

## Mains practice question

Renewable capacity in India is growing faster than the grid that must carry it. In the light of the Green Energy Corridor Phase-III scheme, discuss the challenges of integrating renewable energy into the grid and the role of transmission and storage. (250 words)

### Model answer

On 30 September 2026 the Cabinet approved the ₹1,86,405 crore Green Energy Corridor Phase-III (GEC-III) to evacuate up to 135 GW of renewable energy through intra-State grids and 50 GWh of battery storage.

## Integration challenges
- **Intermittency:** solar peaks at midday and disappears in the evening; wind varies by season.
- **Location mismatch:** solar and wind parks are in Rajasthan, Gujarat and the south, far from many load centres.
- **Congestion and curtailment:** when lines are full, generators are asked to cut output and clean power is wasted.
- **Weak State utilities:** State Transmission Utilities and discoms often lack money to build ahead of demand.
- **Right of way and land:** line projects face local opposition and forest clearances.

## Role of transmission
- Inter-State lines move bulk power across regions; GEC-III strengthens the State-level network so that power reaches consumers.
- Tariff Based Competitive Bidding for greenfield lines brings private capital and lower costs.
- Central support of ₹54,082 crore reduces the burden that would otherwise raise tariffs.

## Role of storage
- 50 GWh of batteries can shift midday solar to evening peaks.
- Storage at generator ends reduces curtailment and the need for new lines.
- Batteries also provide fast frequency support to keep the grid stable.

## Way forward
- Plan transmission ahead of generation.
- Strengthen State utilities' finances and speed up right-of-way approvals.
- Combine batteries with pumped storage, demand response and better forecasting.

Transmission and storage are the bridge between India's renewable capacity and its target of 900 GW of non-fossil capacity by 2035.

## The basics

## Why this matters
A solar park can be built in a year or two. The lines that carry its power often take longer. If the grid cannot take the power, it is curtailed, and the clean energy is lost. Green Energy Corridor Phase-III is the government's largest bet yet on the State-level grid and on batteries.

## Two layers of the grid
India's grid has two layers. The Inter-State and Intra-State Transmission page explains the difference. Inter-State lines move bulk power between regions. Intra-State lines, owned and run by State Transmission Utilities, carry it on to substations and distribution companies. GEC-III is about this second layer.

## Why batteries
Solar output peaks at midday, while demand peaks in the evening. Battery Energy Storage Systems store surplus midday power and release it later. Placed near solar parks, they also ease congestion so that less power is curtailed.

## How it will be built
New (greenfield) lines will be given out through Tariff Based Competitive Bidding: the bidder asking the lowest annual charge wins and then builds, owns, operates and maintains the line. Upgrades to existing (brownfield) assets will be paid on a cost-plus basis.

## Each phase bigger than the last
The earlier rounds are described under Green Energy Corridor Phases I and II.

The jump in scale reflects the target of 900 GW of non-fossil capacity by 2035.

## Sources

- https://www.pmindia.gov.in/en/news_updates/cabinet-approves-green-energy-corridor-phase-iii-scheme-for-development-of-intra-state-transmission-system-with-battery-energy-storage-systems/
- https://www.inkl.com/news/cabinet-clears-rs-1-86-lakh-crore-green-energy-corridor-iii-to-evacuate-135-gw-renewable-power
- https://www.newsbytesapp.com/news/india/union-cabinet-clears-1-86l-crore-green-energy-corridor-project/story
- https://www.pv-magazine.com/2022/01/07/india-cabinet-approves-intrastate-transmission-scheme-backing-20-gw-of-renewable-energy-capacity/