A pretensioned beam 250 mm wide and 300 mm deep is prestressed by 12 wires (each 6 mm diameter) initially stressed to 1200 MPa with their centroid located at 100 mm from the soffit. Estimate the final percentage loss of stress due to elastic shortening, shrinkage, relaxation of steel and creep effect. Assume that the modulus of elasticity of steel and concrete are 210 kN/mm² and 35 kN/mm² respectively, creep coefficient = 1·6, residual shrinkage strain = 3×10⁻⁴ and relaxation of steel stress = 90 MPa.
10 marks · directive: Estimate
The core of a good answer
Total loss ≈ 265.9 MPa out of 1200 MPa, i.e. about 22.2%: elastic shortening 43.4 MPa, shrinkage 63.0 MPa, creep 69.5 MPa and relaxation 90 MPa.
An outline written by upsc.help, not an official UPSC answer; every fact checked by a separate review. How we work
What the question asks
A standard loss-of-prestress computation for a pretensioned member. Each loss is found separately from the stress in concrete at the level of the steel (for elastic shortening and creep), the shrinkage strain (for shrinkage) and the given relaxation value, and the sum is expressed as a percentage of the initial stress. Self-weight moment is neglected, as the data do not give a span.
Answer outline
Introduction
b = 250 mm, D = 300 mm, 12 wires of 6 mm, f_pi = 1200 MPa, eccentricity e = 150 − 100 = 50 mm, E_s = 210 kN/mm², E_c = 35 kN/mm², φ = 1.6, ε_sh = 3×10⁻⁴, relaxation 90 MPa. Gross concrete section used.
Step 1: Section and prestressing force
- A_p = 12 × (π/4) × 6² = 339.3 mm²
- P_i = 1200 × 339.3 = 407.15 kN
- A_c = 250 × 300 = 75,000 mm²; I = 250 × 300³/12 = 5.625×10⁸ mm⁴
- Modular ratio m = 210/35 = 6
Step 2: Concrete stress at the level of steel
- f_c = P/A + P e²/I = 407150/75000 + 407150 × 50²/5.625×10⁸
- f_c = 5.429 + 1.810 = 7.238 MPa
Step 3: Individual losses
- Elastic shortening: m f_c = 6 × 7.238 = 43.43 MPa
- Shrinkage: ε_sh E_s = 3×10⁻⁴ × 210000 = 63.00 MPa
- Creep: φ m f_c = 1.6 × 6 × 7.238 = 69.49 MPa
- Relaxation of steel: 90.00 MPa (given)
Step 4: Total and percentage
- Total loss = 43.43 + 63.00 + 69.49 + 90.00 = 265.92 MPa
- Percentage loss = 265.92/1200 × 100 = 22.16%
- Effective prestress = 1200 − 265.92 ≈ 934 MPa
Conclusion
Final loss ≈ 22.2% of the initial stress. Check: creep loss is φ times the elastic shortening loss as expected (69.49 = 1.6 × 43.43).
Examples and data to cite
- IS 1343:1980 cl. 19.5.2 lists the losses to be allowed for: creep of concrete, shrinkage of concrete, relaxation of steel, elastic shortening at transfer, and friction and slip of anchorage.
- IS 1343:1980 cl. 19.5.2.3: where test values of relaxation are not available, the code gives 1000-hour values (Table 6) to be multiplied by 3 for long-term relaxation; in this question the relaxation loss of 90 MPa is given directly.
Facts to remember
- Elastic shortening loss (pretensioned): calculated on a modular ratio basis using the stress in the adjacent concrete, i.e. m f_c (IS 1343:1980 cl. 19.5.2.4).
- Creep coefficient = creep strain/elastic strain (IS 1343 cl. 3.9); creep loss = E_s × creep strain (cl. 19.5.2.1) = φ × (f_c/E_c) × E_s = φ m f_c.
- Shrinkage loss = E_s × shrinkage strain of concrete (IS 1343:1980 cl. 19.5.2.2).
- f_c = P/A + Pe²/I (neglecting self-weight moment).
- Relaxation loss varies with type of steel, initial prestress, age and temperature and is taken from tests or the code table (IS 1343:1980 cl. 19.5.2.3); here it is given directly.