Explain the ore reserve estimation procedure. How are the tonnage and grade of an ore deposit calculated ?
15 marks · directive: Explain
The core of a good answer
Ore reserve estimation proceeds from drilling, sampling and assay data to a geological model of the orebody, which is divided into blocks or sections whose volume, tonnage (volume x bulk density) and weighted average grade are estimated by methods such as nearest neighbour (polygon), inverse distance weighting or kriging and then summed; the result is classified by geological confidence and economics.
An outline written by upsc.help, not an official UPSC answer; every fact checked by a separate review. How we work
What the question asks
The question asks for the steps of the procedure and the formulas for tonnage and grade. A good answer lists the steps, describes the main estimation methods and gives the formulas with a short illustration.
Answer outline
Introduction
An ore reserve is the economically mineable part of a mineral resource; its estimate needs geological interpretation, sample data, density measurements and economic parameters.
Steps of the procedure
- Collect data: drill holes, trenches, samples, assays, density measurements and survey data, and build a geological model.
- Divide the geological envelopes into a block model of same sized blocks, each with its own grade, density, rock type and confidence level.
- Estimate block values from composites (point grade measurements), choosing a method to suit the required precision and the quantity and quality of data.
- Determine resources and reserves taking project economics into account, and apply dilution and mining loss.
- Classify by confidence: measured, indicated and inferred resources; proved reserves from measured resources and probable reserves from indicated (sometimes measured) resources.
Methods of estimation
- Sections: from the area of ore on parallel sections, the volume between two sections follows from the mean area or the prismoidal formula.
- Nearest neighbour (polygon) method: each block takes the grade of the closest sample; easy by hand but biased above an ore waste cut-off.
- Inverse distance weighting: samples weighted by distance, usually squared; simple and flexible but unreliable with preferential sampling.
- Geostatistical kriging using the variogram gives the best linear unbiased prediction and also an estimation variance; it is computationally intensive.
Calculation of tonnage and grade
- Volume V = area x thickness (or area x distance between sections).
- Tonnage T = V x bulk density ρ (or V / tonnage factor).
- Grade of a hole: G = Σ(gᵢ lᵢ) / Σ lᵢ; block grade weighted by area or volume; deposit grade G = Σ(Tⱼ Gⱼ) / Σ Tⱼ.
- Metal content = T x G.
- Illustration: intercepts of 2.0 m at 1.2 per cent, 1.5 m at 0.8 per cent and 3.0 m at 1.5 per cent Cu give 8.1 / 6.5 = 1.25 per cent Cu.
Conclusion
Reliable estimates depend less on the formula than on sample quality, correct geological boundaries and density data; geostatistics adds a measure of confidence.
Examples and data to cite
- India is among the many countries that have adopted the UN Framework Classification for Resources (developed by UNECE in 1997) as the basis of national resource classification.
- The JORC Code (Australia; JORC Code 2012) regulates reporting on the Australian Securities Exchange and is comparable to Canada's NI 43-101, created after the Bre-X scandal.
Facts to remember
- Prismoidal volume: V = L/6 (A₁ + 4Aₘ + A₂), with Aₘ the mid section area.
- Mean area volume: V = L (A₁ + A₂)/2.
- Tonnage = volume x density; grade = weighted mean; metal = tonnage x grade.
- Kriging gives the best linear unbiased estimate and its kriging variance.