2026 · Management Optional Paper II · 15 marksMainsQuestion 4a

A clock manufacturing company is planning an assembly line to produce 195 clocks per 8-hour shift. The following table gives the work elements, times and immediate predecessors :
Work Elements | Time (in seconds) | Immediate Predecessors
A | 40 | None
B | 80 | A
C | 30 | D, E, F
D | 25 | B
E | 20 | B
F | 15 | B
G | 120 | A
H | 145 | G
I | 130 | H
J | 115 | C, I
(i) What is the desired cycle time (in seconds)?
(ii) What is the theoretical minimum number of stations?
(iii) Show your solution on a precedence diagram.
(iv) What are the efficiency and balance delay of the solution found?

15 marks · directive: Calculate

Answer

The core of a good answer

Desired cycle time = 28,800/195 ≈ 147.69 seconds; theoretical minimum = 720/147.69 = 4.875, so 5 stations; a feasible 5-station balance {A,B,D}, {G,E}, {H}, {I,F}, {C,J} gives efficiency 97.5 per cent and balance delay 2.5 per cent.

An outline written by upsc.help, not an official UPSC answer; every fact checked by a separate review. How we work

What the question asks

An assembly line balancing problem: compute cycle time from the required output, the theoretical minimum number of stations from total work content, draw the precedence network, assign elements to stations with a heuristic (largest eligible element first) without exceeding the cycle time, then compute efficiency and balance delay.

Answer outline

Introduction

Given: output 195 clocks per 8-hour shift (28,800 seconds), ten work elements with total work content 40 + 80 + 30 + 25 + 20 + 15 + 120 + 145 + 130 + 115 = 720 seconds.

Step 1: Desired cycle time (i)

Step 2: Theoretical minimum stations (ii)

Step 3: Precedence diagram (iii)

Step 4: Station assignment (largest eligible element that fits, C = 147.69)

Step 5: Efficiency and balance delay (iv)

Conclusion

Five stations, the theoretical minimum, are achieved, so the balance is optimal in number of stations: efficiency 97.5 per cent, balance delay 2.5 per cent. Check: each station load is at most 147.69 seconds and all precedence relations hold; the assignment was rechecked by a Python simulation of the heuristic.