A spare parts store faces stochastic demand. Annual demand is normally distributed with mean (μ) = 2400 units and standard deviation σ_-D = 300 units. Lead time is fixed at 2 weeks.
Assume 50 working weeks/year. Ordering cost = ₹ 800/order, Holding cost = ₹ 18/unit/year, Unit cost = ₹ 240, and Stockout cost = ₹ 90/unit short. The store operates with a continuous review policy.
(i) Compute the Economic Order Quantity.
(ii) Determine the demand during lead time (mean and standard deviation).
(iii) If the desired service level is 95% (z = 1·645), calculate the safety stock and reorder point.
(iv) Compute the total annual inventory cost (ordering + holding + safety stock holding). By how much does safety stock inflate total holding cost compared to the zero safety stock scenario ?
20 marks · directive: Compute
The core of a good answer
EOQ = √(2 × 2400 × 800/18) = 462 units; lead-time demand has mean 96 and standard deviation 300√(2/50) = 60 units; safety stock 1·645 × 60 = 98·7 units and reorder point 194·7 ≈ 195 units; total annual cost ₹ 4,157 + ₹ 4,157 + ₹ 1,777 = ₹ 10,090, with safety stock raising holding cost by ₹ 1,777 (42·7%).
An outline written by upsc.help, not an official UPSC answer; every fact checked by a separate review. How we work
What the question asks
A continuous review (Q, R) model with normal demand. Use EOQ for the order quantity, scale annual mean and variance to the lead time (mean × L, standard deviation × √L), set safety stock = zσ_L, reorder point = mean + safety stock, and add the holding cost of safety stock to the EOQ costs.
Answer outline
Introduction
D = 2400 units/year, σ_D = 300 units/year, L = 2 weeks = 2/50 year, S = ₹ 800, H = ₹ 18 per unit per year.
Step 1: EOQ (i)
- Q* = √(2DS/H) = √(2 × 2400 × 800/18) = √213333 = 461·9 ≈ 462 units
- Orders per year = 2400/461·9 = 5·2; cycle about 9·6 weeks
Step 2: Lead-time demand (ii)
- μ_L = 2400 × 2/50 = 96 units
- σ_L = 300 × √(2/50) = 300 × 0·2 = 60 units (independent weekly demands)
Step 3: Safety stock and reorder point (iii)
- SS = zσ_L = 1·645 × 60 = 98·7 ≈ 99 units
- ROP = μ_L + SS = 96 + 98·7 = 194·7 ≈ 195 units
Step 4: Annual cost (iv)
- Ordering: (D/Q)S = 5·196 × 800 = ₹ 4,156·9
- Cycle holding: (Q/2)H = 230·9 × 18 = ₹ 4,156·9
- Safety stock holding: SS × H = 98·7 × 18 = ₹ 1,776·6
- Total = ₹ 10,090·4 per year
Step 5: Effect of safety stock
- Holding cost rises from ₹ 4,156·9 to ₹ 5,933·5, an increase of ₹ 1,776·6 or 42·7%
- Total relevant cost rises from ₹ 8,313·8 to ₹ 10,090·4 (21·4%)
- Stockout cost ₹ 90 and unit cost ₹ 240 do not enter these items
Conclusion
EOQ 462 units, lead-time demand 96 ± 60 units, SS 98·7 units, ROP 194·7 units, total cost about ₹ 10,090 per year, safety stock adding 42·7% to holding cost. Check: at EOQ ordering and cycle holding costs are equal. (Recomputed in Python.)
Examples and data to cite
- At the EOQ the ordering and cycle holding costs are equal (₹ 4,156·9 each here), which is a quick check on the arithmetic.
Facts to remember
- EOQ = √(2DS/H): ordering cost (D/Q)S plus holding cost (Q/2)H is least there, where the two are equal.
- Lead-time demand: μ_L = dL, σ_L = σ_d√L for independent, normally distributed demand per period.
- Reorder point = demand during lead time + safety stock; safety stock = zσ_L.
- A 95% service level corresponds to z ≈ 1·65 (the paper gives 1·645).