2014 · GS3 · 12.5 marksMains

Environmental Impact Assessment studies are increasingly undertaken before a project is cleared by the Government. Discuss the environmental impacts of coal-fired thermal plants located at coal pitheads.

Question source: superkalam.com

Write a timed answer in the app

Current affairs to use in your answer

Centre resumes appraising pending post facto green clearances after Supreme Court ruling · 3 October 2026 · Covers one part · use it in the introduction

Use it to open by explaining why EIA must precede clearance: assessment after construction can only legitimise or mitigate harm, not prevent it.

  • The EIA Notification, 2006 requires clearance before any work begins, after screening, scoping, public consultation and appraisal by expert committees, so that harm is judged before it happens.
  • In Alembic Pharmaceuticals v Rohit Prajapati (2020) the Supreme Court called ex post facto clearances contrary to the precautionary principle, which applies with force to large polluting plants.